Caltrans Logo

San Francisco Paratransit Vehicle Mobile Data Computer (MDC) Project

Description: Purchase and install Mobile Data Computers with Global Positioning System capability on 120 SF Paratransit Vans

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
03, 08
Assembly District 12, 13
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUZANNE S. WANG (415) 701-4541   SUZANNE.WANG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $174 $174
Non-bond Funding
State/Federal*
$0 $696 $696
 
Total**** $0 $871 $871

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $871 $871 $871 $871 $0
 
Total* $0 $871 $871 $871 $871 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2010 

06/30/2011 
 

 
12/01/2010 

06/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2011 

06/30/2012 
03/07/2012 

03/07/2012 
01/01/2012 

09/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2012 

12/31/2012 
03/07/2012 

09/19/2014 
12/15/2013 

02/15/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 5

Bond Funding Cost
Adopted:
$0
Current Approved:
$174,116
Actual Expenditures:
$174,116

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31