BART - Oakland Airport Connector

Description: Provide improved access from BART to Oakland Int'l Airport using an Automated Guideway Technology

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94604
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  65    65  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KENNETH DURON (510) 464-6083   BOARDOFDIRECTORS@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $54 $54
PTMISEA-99313
$12,801 $0 $12,801
PTMISEA-99314
$5,400 $0 $5,400
Non-bond Funding
State/Federal*
$0 $85,509 $85,509
Local**
$0 $394,703 $394,703
 
Total**** $18,201 $480,266 $498,467

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $16,932 $16,932 $16,932 $16,932 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $12,059 $12,059 $12,059 $12,059 $0
Construction
$18,201 $451,275 $469,476 $469,476 $469,476 $0
 
Total* $18,201 $480,266 $498,467 $498,467 $498,467 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/15/2000 

04/30/2009 
 

 
07/15/2000 

04/30/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/30/2004 

12/09/2009 
 

04/09/2015 
07/30/2004 

04/30/2015 
100   

 


Begin Construction Phase

End Construction Phase
01/15/2010 

07/30/2013 
04/08/2011 

03/05/2014 
06/01/2011 

05/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2013 

07/30/2014 
09/23/2019 

09/23/2019 
12/31/2014 

06/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 65 65

Bond Funding Cost
Adopted:
$18,201,000
Current Approved:
$18,201,000
Actual Expenditures:
$18,201,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31