Caltrans Logo

CNG Fueling Station

Description: Install slow fill fueling station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Auburn Bernie Schroeder (530) 823-4211   bschroeder@auburn.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$75 $0 $75
Non-bond Funding
Local**
$228 $3 $231
 
Total**** $303 $3 $306

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$10 $0 $10 $10 $10 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$293 $3 $296 $306 $306 $-10
 
Total* $303 $3 $306 $316 $316 $-10

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2007 

01/01/2008 
 

05/01/2008 
08/01/2007 

05/01/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2008 

03/01/2008 
05/01/2008 

06/11/2008 
05/01/2008 

06/11/2008 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Useful Life (years) 20

Bond Funding Cost
Adopted:
$75,000
Current Approved:
$75,000
Actual Expenditures:
$75,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31