County Express Bus Stop Shelter Program

Description: Purchase and install a bus stop shelter for use by county express public transit service. The shelter is 13' and includes a bench and ADA-accessible area. The shelter also has solar lighting.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
28
Assembly District 12
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MARY GILBERT (831) 637-7665   MARY@SANBENITOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$2 $0 $2
Non-bond Funding
State/Federal*
$0 $25 $25
 
Total**** $2 $25 $27

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2 $25 $27 $2 $2 $25
 
Total* $2 $25 $27 $2 $2 $25

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

10/01/2013 
 

 
07/01/2012 

10/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

10/01/2013 
04/12/2016 

04/12/2016 
10/01/2013 

03/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 10

Bond Funding Cost
Adopted:
$1,624
Current Approved:
$1,624
Actual Expenditures:
$1,624

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31