Chaffey College Transit Center

Description: Construct new transit center at Chaffey College

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92411
 
Senate District
32
Assembly District 62
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Omnitrans Rohan Kuruppu (909) 379-7251   rohan.kruruppu@omnitrans.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,715 $-271 $1,444
PTMISEA-99314
$1,285 $0 $1,285
Non-bond Funding
 
Total**** $3,000 $-271 $2,729

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$915 $-915 $0 $0 $0 $0
Design(PS&E)
$0 $307 $307 $307 $307 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,085 $337 $2,422 $2,422 $2,422 $0
 
Total* $3,000 $-271 $2,729 $2,729 $2,729 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2007 

01/01/2008 
03/14/2011 

03/14/2011 
11/01/2007 

01/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

04/01/2008 
03/14/2011 

09/05/2012 
01/01/2008 

02/14/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
09/01/2008 

05/01/2009 
03/14/2011 

03/28/2014 
06/01/2010 

12/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

12/01/2009 
03/29/2013 

03/28/2014 
04/01/2013 

12/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)

Bond Funding Cost
Adopted:
$3,000,000
Current Approved:
$2,729,249
Actual Expenditures:
$2,729,249

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31