Rueben Campos Transit Center

Description: safety improvements at the transit center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92411
 
Senate District
32
Assembly District 62
Congressional District 35
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MAURICE MANSION (909) 379-7169   MAURICE.MANSION@OMNITRANS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $32 $32
PTMISEA-99313
$0 $271 $271
Non-bond Funding
 
Total**** $0 $303 $303

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $303 $303 $303 $303 $0
 
Total* $0 $303 $303 $303 $303 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

03/31/2016 
02/10/2017 

02/10/2017 
12/01/2016 

04/01/2017 
 

 


Begin Closeout Phase

End Closeout Phase
03/31/2016 

05/30/2016 
 

09/12/2018 
03/31/2016 

09/30/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1

Bond Funding Cost
Adopted:
$0
Current Approved:
$270,751
Actual Expenditures:
$270,751

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31