Proposition 1B
Bond Accountability
Purchase 3 Rail Cars |
Description: New rail cars for San Bernardino Line
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | San Bernardino |
Zip Code | 92401 |
Senate District |
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38 |
Assembly District | 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80 |
Congressional District | 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 34, 38, 39, 40, 41, 42, 43, 44, 47, 48, 49 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | 12 | |
Increased Ridership | 7 | |
Useful Life (years) | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
San Bernardino Associated Governments | Mitch Alderman | (909) 884-8276 | malderman@sanbag.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $186 | $186 | ||||
PTMISEA-99313 |
$5,500 | $0 | $5,500 | ||||
Non-bond Funding | |||||||
Total**** | $5,500 | $186 | $5,686 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,500 | $186 | $5,686 | $5,686 | $5,686 | $0 | |
Total* | $5,500 | $186 | $5,686 | $5,686 | $5,686 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2008 06/01/2010 |
09/28/2009 05/05/2011 |
09/26/2008 10/31/2011 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2010 06/01/2011 |
05/05/2011 03/01/2019 |
10/31/2011 03/29/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | 12 | |
Increased Ridership | 7 | |
Useful Life (years) | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,500,000 |
Current Approved: |
$5,500,000 |
Actual Expenditures: |
$5,500,000 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31