Caltrans Logo

Particulate Filter Systems

Description: Purchase & install 14 lean-nox catalyst/diesel particulate systems

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City
Zip Code
 
Senate District
05, 14
Assembly District 15, 17, 26
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Number of Buses Rehabed  17      
Reduce Emissions (percent)        
Reduced Emissions        
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
San Joaquin Regional Transit District Tammy Kramp 209-467-6686   tkramp@sanjoaquinRTD.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$410 $0 $410
Non-bond Funding
State/Federal*
$28 $0 $28
 
Total**** $438 $0 $438

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$438 $0 $438 $438 $438 $-0
 
Total* $438 $0 $438 $438 $438 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2008 

03/30/2009 
01/07/2009 

01/07/2009 
06/30/2008 

10/31/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
03/30/2009 

06/30/2009 
01/07/2009 

01/07/2009 
10/31/2008 

12/01/2008 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Buses Rehabed 17
Reduce Emissions (percent)
Reduced Emissions
Useful Life (years) 12

Bond Funding Cost
Adopted:
$410,176
Current Approved:
$410,176
Actual Expenditures:
$410,176

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31