Transit Station Restrooms

Description: Construct restrooms accessed by both Greyhound Bus line & Amtrak passengers

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City Paso Robles
Zip Code 93446
 
Senate District
15
Assembly District 33
Congressional District 22
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  35    30  
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of El Paso de Robles James Throop (805) 237-3999 X650   jthroop@prcity.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$146 $0 $146
PTMISEA-99314
$13 $0 $13
Non-bond Funding
State/Federal*
$0 $45 $45
 
Total**** $159 $45 $204

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $26 $26 $-11
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$144 $45 $189 $133 $133 $56
 
Total* $159 $45 $204 $159 $159 $45

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

07/30/2008 
 

03/25/2011 
01/01/2008 

01/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

01/30/2009 
03/25/2011 

03/25/2011 
02/01/2010 

05/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2009 

04/30/2009 
03/25/2011 

03/25/2011 
06/01/2010 

08/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 35 30
Useful Life (years) 30

Bond Funding Cost
Adopted:
$158,765
Current Approved:
$158,765
Actual Expenditures:
$158,765

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31