Caltrans Logo

Paint Transit Bus

Description: Re-paint three 35 ft RAB buses with new exterior paint & graphic design consistent with current 2009-10 Marketing Plan

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96049
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GARY OTREMBA (530) 225-4955   GOTREMBA@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$2 $0 $2
PTMISEA-99313
$27 $0 $27
PTMISEA-99314
$1 $0 $1
Non-bond Funding
 
Total**** $30 $0 $30

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$30 $0 $30 $30 $30 $0
 
Total* $30 $0 $30 $30 $30 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2009 

12/31/2009 
08/24/2011 

08/24/2011 
09/01/2009 

09/30/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2010 

06/01/2011 
08/24/2011 

08/24/2011 
01/01/2011 

06/30/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15

Bond Funding Cost
Adopted:
$30,000
Current Approved:
$30,000
Actual Expenditures:
$30,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31