Caltrans Logo

Transit Bus Purchase

Description: Provide match money required for use of 5307/5310/5311 funds to purchase 10 demand response vans, four 40ft fixed route buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96049
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ZACH BONNIN (530) 225-7116   ZBONNIN@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$376 $-124 $252
PTMISEA-99314
$19 $0 $19
Non-bond Funding
State/Federal*
$0 $1,805 $1,805
 
Total**** $395 $1,687 $2,082

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$395 $1,687 $2,082 $2,082 $2,082 $0
 
Total* $395 $1,687 $2,082 $2,082 $2,082 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2009 

06/30/2010 
10/06/2011 

10/06/2011 
09/01/2009 

12/01/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2010 

12/31/2010 
11/16/2011 

11/16/2011 
01/01/2011 

06/01/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 25

Bond Funding Cost
Adopted:
$395,362
Current Approved:
$270,976
Actual Expenditures:
$270,976

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31