CNG Transit Buses

Description: Purchase one CNG transit bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City
Zip Code
 
Senate District
16, 18
Assembly District 34
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      50  
Number of Buses Purchased for Replacment  2      
Useful Life (years)  7      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Tulare County Association of Governements Marvin Demmers 559-733-6291   mdemmers@co.tulare.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$157 $0 $157
Non-bond Funding
State/Federal*
$42 $0 $42
Local**
$47 $1 $48
 
Total**** $246 $1 $247

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$246 $1 $247 $247 $247 $0
 
Total* $246 $1 $247 $247 $247 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

03/31/2008 
02/23/2009 

05/17/2010 
04/01/2008 

04/30/2008 
 

 


Begin Closeout Phase

End Closeout Phase
07/01/2008 

10/01/2008 
05/17/2010 

05/17/2010 
11/11/2008 

02/01/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 50
Number of Buses Purchased for Replacment 2
Useful Life (years) 7

Bond Funding Cost
Adopted:
$157,028
Current Approved:
$157,028
Actual Expenditures:
$157,028

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31