Caltrans Logo

Bus Cover Shop

Description: "Construct bus cover shop, bus storage"

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Exeter
Zip Code 93221
 
Senate District
18
Assembly District 34
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost      50  
Useful Life (years)  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Exeter Felix Ortiz (559) 592-2523   felizexe@aol.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$84 $-9 $75
PTMISEA-99314
$1 $0 $1
Non-bond Funding
 
Total**** $85 $-7 $78

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$85 $-7 $78 $78 $78 $0
 
Total* $85 $-7 $78 $78 $78 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

10/31/2008 
05/20/2010 

05/20/2010 
04/01/2008 

10/31/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2008 

10/31/2008 
05/20/2010 

05/20/2010 
10/01/2008 

10/31/2008 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 50
Useful Life (years) 25

Bond Funding Cost
Adopted:
$87,515
Current Approved:
$75,938
Actual Expenditures:
$75,938

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31