Yard Bus Maint. Facility |
Description: Maint. facility expansion
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | Porterville |
Zip Code | 93257 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | |
Reduced Operating/Maintenance Cost | 67 | |
Useful Life (years) | 20 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
City of Porteville | Linda Clark | (559) 782-7466 | lclark@ci.porteville.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $12 | $12 | ||||
PTMISEA-99313 |
$404 | $0 | $404 | ||||
PTMISEA-99314 |
$30 | $0 | $30 | ||||
Non-bond Funding | |||||||
State/Federal* |
$580 | $71 | $651 | ||||
Local** |
$145 | $18 | $163 | ||||
Total**** | $1,159 | $100 | $1,259 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$89 | $0 | $89 | $106 | $106 | $-17 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,070 | $100 | $1,170 | $1,170 | $1,170 | $0 | |
Total* | $1,159 | $100 | $1,259 | $1,277 | $1,277 | $-17 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2008 10/30/2008 |
01/21/2010 01/21/2010 |
11/01/2008 09/01/2009 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/30/2008 12/30/2008 |
01/21/2010 |
07/01/2009 01/01/2010 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | |
Reduced Operating/Maintenance Cost | 67 | |
Useful Life (years) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
$434,207 |
Current Approved: |
$434,207 |
Actual Expenditures: |
$434,207 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31