Bus Shelters

Description: Construction & placement of 4 bus shelters & 6-8 benches/Amended 4 bus shelters, funds from cycle 2 now included in cycle 1

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Calaveras
City San Andreas
Zip Code 95249
 
Senate District
01
Assembly District 26
Congressional District 03
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      6  
Useful Life (years)  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Calaveras County Public Works Department Michael H. Miller (209) 754-6401   mhmiller@co.calaveras.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$125 $0 $125
Non-bond Funding
State/Federal*
$78 $86 $164
 
Total**** $203 $89 $291

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$203 $89 $291 $291 $291 $0
 
Total* $203 $89 $291 $291 $291 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2007 

01/01/2008 
03/30/2010 

03/30/2010 
03/01/2008 

08/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/15/2008 

01/29/2009 
10/13/2009 

10/13/2009 
12/01/2008 

11/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2009 

03/15/2009 
03/09/2011 

03/09/2011 
11/15/2010 

12/22/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 6
Useful Life (years) 10

Bond Funding Cost
Adopted:
$124,763
Current Approved:
$124,763
Actual Expenditures:
$124,763

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31