Caltrans Logo

Shafter Transit Connect Electric Dial-A-Ride

Description: Three 220 volt 70 amp recharge stations and Three Zenith Motors electric vans with capacity for 8 riders, and related equipment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
18
Assembly District 32
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    19  
Reduced Emissions      50  
Reduced Operating/Maintenance Cost      50  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BETTY DENNISON (661) 862-8616   BETTY DENNISON
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$272 $108 $380
PTMISEA-99314
$25 $7 $32
Non-bond Funding
State/Federal*
$0 $6 $6
 
Total**** $296 $123 $420

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$296 $123 $420 $420 $420 $0
 
Total* $296 $123 $420 $420 $420 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2011 

12/01/2011 
12/08/2015 

12/08/2015 
03/01/2015 

12/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2012 

05/01/2012 
12/08/2015 

06/30/2017 
07/01/2015 

05/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

06/02/2012 
12/08/2015 

02/26/2018 
06/01/2016 

06/30/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 19
Reduced Emissions 50
Reduced Operating/Maintenance Cost 50

Bond Funding Cost
Adopted:
$296,467
Current Approved:
$411,741
Actual Expenditures:
$411,741

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31