Colusa Transit Bus Covered Parking with Solar Panel Roofing

Description: Install covered parking shelters for buses with solar PV system on roof.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Colusa
City Colusa
Zip Code 95932
 
Senate District
04
Assembly District 03
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership  5      
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  25    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE AZEVEDO (530) 458-0471   MJAZEVEDO@COUNTYOFCOLUSA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$344 $143 $487
PTMISEA-99314
$22 $56 $78
Non-bond Funding
 
Total**** $366 $200 $566

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$14 $0 $14 $13 $13 $1
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$352 $200 $552 $552 $552 $-0
 
Total* $366 $200 $566 $566 $566 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2014 

02/25/2014 
 

 
02/01/2014 

02/25/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2014 

04/01/2014 
09/16/2017 

09/16/2017 
10/01/2017 

04/17/2018 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2014 

08/01/2014 
09/25/2019 

08/26/2021 
09/01/2018 

05/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2014 

10/01/2014 
02/02/2023 

02/02/2023 
05/01/2023 

05/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 5
Reduced Emissions 10
Reduced Operating/Maintenance Cost 25 10

Bond Funding Cost
Adopted:
$366,000
Current Approved:
$565,612
Actual Expenditures:
$565,612

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31