Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Commuter bus replacement |
Description: "Purchase 5 new commuter, diesel powered buses"
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
El Dorado |
City | Diamond Springs |
Zip Code | 95619 |
Senate District |
01 |
Assembly District | 04, 10 |
Congressional District | 05 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | ||
Number of Buses Purchased for Replacment | 7 | |
Useful Life (years) | 20 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
El Dorado County Transit Authority | Matt Mauk | (530) 642-5383 X201 | mmauk@eldoradotransit.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $39 | $39 | ||||
PTMISEA-99313 |
$1,143 | $0 | $1,143 | ||||
PTMISEA-99314 |
$112 | $0 | $112 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,895 | $48 | $1,943 | ||||
Total**** | $3,150 | $87 | $3,237 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,150 | $87 | $3,237 | $2,592 | $2,592 | $645 | |
Total* | $3,150 | $87 | $3,237 | $2,592 | $2,592 | $645 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/02/2008 06/10/2010 |
09/22/2009 07/15/2009 |
09/22/2008 07/15/2009 |
60 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2010 12/31/2010 |
11/02/2009 06/30/2010 |
11/02/2009 12/31/2010 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | ||
Number of Buses Purchased for Replacment | 7 | |
Useful Life (years) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,254,656 |
Current Approved: |
$1,254,656 |
Actual Expenditures: |
$1,254,656 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31