Commuter bus replacement

Description: "Purchase 5 new commuter, diesel powered buses"

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Diamond Springs
Zip Code 95619
 
Senate District
01
Assembly District 04, 10
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
Number of Buses Purchased for Replacment  7      
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
El Dorado County Transit Authority Matt Mauk (530) 642-5383 X201   mmauk@eldoradotransit.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $39 $39
PTMISEA-99313
$1,143 $0 $1,143
PTMISEA-99314
$112 $0 $112
Non-bond Funding
State/Federal*
$1,895 $48 $1,943
 
Total**** $3,150 $87 $3,237

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,150 $87 $3,237 $2,592 $2,592 $645
 
Total* $3,150 $87 $3,237 $2,592 $2,592 $645

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/02/2008 

06/10/2010 
09/22/2009 

07/15/2009 
09/22/2008 

07/15/2009 
60   

 


Begin Closeout Phase

End Closeout Phase
10/01/2010 

12/31/2010 
11/02/2009 

06/30/2010 
11/02/2009 

12/31/2010 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)
Number of Buses Purchased for Replacment 7
Useful Life (years) 20

Bond Funding Cost
Adopted:
$1,254,656
Current Approved:
$1,254,656
Actual Expenditures:
$1,254,656

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31