Clovis Transit Rolling Stock

Description: Purchase 4- 27 foot- diesel & 3- 32 foot- diesel buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Clovis
Zip Code 93611
 
Senate District
14
Assembly District 29
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1    5  
Number of New Buses Purchased for Expansion        
Useful Life (years)  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Clovis Shonna Halterman (559) 324-2767   shonnah@cityofclovis.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $15 $15
PTMISEA-99313
$726 $0 $726
PTMISEA-99314
$9 $0 $9
Non-bond Funding
State/Federal*
$563 $356 $919
 
Total**** $1,298 $371 $1,669

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,298 $371 $1,669 $803 $803 $865
 
Total* $1,298 $371 $1,669 $803 $803 $865

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/15/2008 

04/01/2009 
04/29/2010 

04/29/2010 
06/17/2008 

03/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2009 

06/01/2009 
04/29/2010 

04/29/2010 
04/01/2009 

05/01/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1 5
Number of New Buses Purchased for Expansion
Useful Life (years) 10

Bond Funding Cost
Adopted:
$735,257
Current Approved:
$735,257
Actual Expenditures:
$735,257

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31