Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Rolling Stock Procurement |
Description: Purchase 2 - 35' Transit Buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Humboldt |
City | Arcata |
Zip Code | 95521 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Decreased Maintenance Cost (percent) | ||
Number of Buses Purchased for Replacment | 2 | |
Reduce Emissions (percent) | ||
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
City of Arcata | Larry Pardi | (707) 822-3775 | lpardi@arcatacityhall.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $7 | $7 | ||||
PTMISEA-99313 |
$209 | $0 | $209 | ||||
PTMISEA-99314 |
$17 | $0 | $17 | ||||
Non-bond Funding | |||||||
State/Federal* |
$424 | $0 | $424 | ||||
Local** |
$100 | $16 | $116 | ||||
Total**** | $750 | $23 | $773 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$750 | $23 | $773 | $768 | $768 | $5 | |
Total* | $750 | $23 | $773 | $768 | $768 | $5 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2008 10/01/2008 |
02/17/2010 |
10/01/2008 11/28/2009 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
02/17/2010 02/17/2010 |
01/25/2010 01/25/2010 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Decreased Maintenance Cost (percent) | ||
Number of Buses Purchased for Replacment | 2 | |
Reduce Emissions (percent) | ||
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$225,758 |
Current Approved: |
$225,758 |
Actual Expenditures: |
$225,758 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31