1 CNG Bus Replacement

Description: Purchase one 29-foot CNG replacement bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Delano
Zip Code 93215
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      22  
Reduced Operating/Maintenance Cost  9      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PHIL NEWHOUSE (661) 721-2602   PNEWHOUSE@CITYOFDELANO.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$231 $0 $231
PTMISEA-99314
$8 $0 $8
Non-bond Funding
State/Federal*
$61 $-61 $0
Local**
$0 $209 $209
 
Total**** $300 $148 $448

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$300 $148 $448 $448 $448 $0
 
Total* $300 $148 $448 $448 $448 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/06/2009 

12/31/2009 
10/14/2014 

10/14/2014 
05/01/2010 

06/28/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
 

12/31/2009 
10/14/2014 

10/14/2014 
07/01/2011 

09/18/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 22
Reduced Operating/Maintenance Cost 9

Bond Funding Cost
Adopted:
$239,169
Current Approved:
$239,169
Actual Expenditures:
$239,169

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31