Compressed Natural Gas Bus Procurement

Description: Purchase 19 compressed natural gas buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City
Zip Code
 
Senate District
16, 18
Assembly District 30, 32
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  15      
Number of Buses Purchased for Replacment  19      
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Golden Empire Transit District Steven Woods 661-324-9874   stwoods@zeus.kern.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $9 $9
PTMISEA-99313
$3,395 $0 $3,395
PTMISEA-99314
$415 $0 $415
Non-bond Funding
State/Federal*
$4,545 $0 $4,545
Local**
$0 $0 $0
 
Total**** $8,355 $9 $8,363

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,355 $9 $8,363 $13,393 $13,393 $-5,030
 
Total* $8,355 $9 $8,363 $13,393 $13,393 $-5,030

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/17/2008 

09/30/2009 
 

 
07/17/2008 

09/30/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
10/30/2009 

12/15/2009 
07/25/2019 

07/25/2019 
02/05/2010 

08/05/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 15
Number of Buses Purchased for Replacment 19
Useful Life (years) 12

Bond Funding Cost
Adopted:
$3,809,887
Current Approved:
$3,809,887
Actual Expenditures:
$3,809,887

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31