CNG Bus Service Area Enclosure(Bakerfield)

Description: CNG Bus Service Area Enclosure at Central Shop Facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code
 
Senate District
18
Assembly District 32
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Kern County Public Transportation Department Jeanette Downs 661-862-8839   downsje@co.kern.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$439 $-435 $4
Non-bond Funding
 
Total**** $439 $-435 $4

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$439 $-435 $4 $4 $4 $0
 
Total* $439 $-435 $4 $4 $4 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

09/23/2009 
02/15/2008 

06/30/2009 
80   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

02/28/2009 
05/13/2010 

05/13/2010 
02/15/2010 

09/30/2010 
10   

 


Begin Closeout Phase

End Closeout Phase
03/01/2009 

04/01/2009 
11/30/2010 

12/31/2010 
06/15/2010 

12/31/2010 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Useful Life (years) 20

Bond Funding Cost
Adopted:
$438,763
Current Approved:
$3,671
Actual Expenditures:
$3,671

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31