Trolly Stop Improvements

Description: Install 3 handicap accessilbe bus stops and signage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Claremont
Zip Code 91711
 
Senate District
29
Assembly District 59
Congressional District 26
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      100  
Safety Improvement (percent)  100      
Useful Life (years)  40      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Claremont Scott Carroll (909) 399-5431   scarroll@ci.claremont.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$31 $0 $31
Non-bond Funding
State/Federal*
$34 $0 $34
 
Total**** $65 $0 $65

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$65 $0 $65 $31 $31 $34
 
Total* $65 $0 $65 $31 $31 $34

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

08/01/2008 
 

 
09/22/2008 

10/17/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2008 

09/15/2008 
 

 
01/04/2009 

04/15/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100
Safety Improvement (percent) 100
Useful Life (years) 40

Bond Funding Cost
Adopted:
$30,722
Current Approved:
$30,722
Actual Expenditures:
$30,722

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31