Bus Replacement Alternative Fuel |
Description: Purchased 47 total buses - 45 CNG and 2 Battery Electric.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | 90801 |
Senate District |
25, 27, 28, 35 |
Assembly District | 50, 52, 54, 55, 56, 57, 58, 67 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Decreased Maintenance Cost (percent) | 50 | |
Increase System Reliability | 40 | |
Useful Life (years) | 12 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Long Beach Transit | Ms. Dana Lee | (562) 599-8571 | dlee@lbtransit.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $206 | $206 | ||||
PTMISEA-99314 |
$3,710 | $9,430 | $13,140 | ||||
Non-bond Funding | |||||||
Local** |
$2,574 | $5,393 | $7,966 | ||||
Total**** | $6,284 | $15,028 | $21,313 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,284 | $15,028 | $21,313 | $21,313 | $21,313 | $0 | |
Total* | $6,284 | $15,028 | $21,313 | $21,313 | $21,313 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2008 01/01/2010 |
08/28/2013 09/05/2014 |
10/01/2012 06/30/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2010 04/01/2010 |
02/18/2022 02/18/2022 |
09/30/2021 02/18/2022 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Decreased Maintenance Cost (percent) | 50 | |
Increase System Reliability | 40 | |
Useful Life (years) | 12 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,710,248 |
Current Approved: |
$13,139,786 |
Actual Expenditures: |
$13,139,786 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31