Bus Replacement Alternative Fuel

Description: Purchased 47 total buses - 45 CNG and 2 Battery Electric.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Long Beach
Zip Code 90801
 
Senate District
25, 27, 28, 35
Assembly District 50, 52, 54, 55, 56, 57, 58, 67
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  50      
Increase System Reliability      40  
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Long Beach Transit Ms. Dana Lee (562) 599-8571   dlee@lbtransit.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $206 $206
PTMISEA-99314
$3,710 $9,430 $13,140
Non-bond Funding
Local**
$2,574 $5,393 $7,966
 
Total**** $6,284 $15,028 $21,313

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,284 $15,028 $21,313 $21,313 $21,313 $0
 
Total* $6,284 $15,028 $21,313 $21,313 $21,313 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2008 

01/01/2010 
08/28/2013 

09/05/2014 
10/01/2012 

06/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2010 

04/01/2010 
02/18/2022 

02/18/2022 
09/30/2021 

02/18/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 50
Increase System Reliability 40
Useful Life (years) 12

Bond Funding Cost
Adopted:
$3,710,248
Current Approved:
$13,139,786
Actual Expenditures:
$13,139,786

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31