New Flyer Bus Purchase

Description: Purchase six 40 -ft & three 35-ft hybrid buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 56
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduce Emissions (percent)  90      
Reduced Emissions      90  
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Norwalk Theresa Clark (562) 929-5601   tclark@ci.norwalk.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $9 $9
PTMISEA-99314
$517 $0 $517
Non-bond Funding
State/Federal*
$4,657 $106 $4,763
 
Total**** $5,175 $115 $5,290

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,175 $115 $5,290 $526 $526 $4,763
 
Total* $5,175 $115 $5,290 $526 $526 $4,763

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

12/01/2009 
09/16/2010 

09/16/2010 
09/08/2008 

08/31/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2010 

02/01/2010 
09/16/2010 

09/16/2010 
09/01/2010 

10/01/2010 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduce Emissions (percent) 90
Reduced Emissions 90
Useful Life (years) 12

Bond Funding Cost
Adopted:
$517,479
Current Approved:
$517,479
Actual Expenditures:
$517,479

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31