Caltrans Logo

Big Blue Bus-Bus Replacement

Description: Replace 21 1995 Nova Diesel buses with 21 articulated LNG buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Santa Monica
Zip Code 90401
 
Senate District
23
Assembly District 41
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  60    60  
Increased Ridership  20    20  
Reduce Emissions (percent)  35      
Reduced Emissions      35  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Santa Monica David Feinberg (310) 458-1975 X5848   david.feinberg@smgov.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $244 $244
PTMISEA-99314
$2,670 $0 $2,670
Non-bond Funding
State/Federal*
$0 $12,815 $12,815
Local**
$2,092 $2,000 $4,092
 
Total**** $4,763 $15,059 $19,821

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,763 $15,059 $19,821 $2,914 $2,914 $16,907
 
Total* $4,763 $15,059 $19,821 $2,914 $2,914 $16,907

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2008 

12/01/2009 
 

03/29/2013 
06/09/2009 

03/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
 

03/01/2010 
03/29/2013 

03/29/2013 
09/30/2012 

02/15/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 60 60
Increased Ridership 20 20
Reduce Emissions (percent) 35
Reduced Emissions 35

Bond Funding Cost
Adopted:
$2,670,287
Current Approved:
$2,670,287
Actual Expenditures:
$2,670,287

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31