Caltrans Logo

Passenger Bus Shelter

Description: Purchase & install 29 Bus Shelters

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Reduce Emissions (percent)  10      
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Merced County Association of Governments Janet Kasper (209) 385-7600   JKasper@co.merced.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$160 $33 $193
Non-bond Funding
State/Federal*
$0 $68 $68
 
Total**** $160 $102 $262

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$160 $102 $262 $262 $262 $0
 
Total* $160 $102 $262 $262 $262 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

08/01/2008 
 

10/26/2009 
04/01/2008 

03/31/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2008 

09/01/2008 
10/06/2011 

10/06/2011 
03/01/2011 

03/31/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Reduce Emissions (percent) 10
Useful Life (years) 20

Bond Funding Cost
Adopted:
$160,100
Current Approved:
$160,100
Actual Expenditures:
$160,100

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31