Bus Hoists & Administration Buidling

Description: Modular building & 2 portable hoists

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  20      
Increase System Reliability        
Increase System Reliability (percent)  20      
Reduced Operating/Maintenance Cost        
Useful Life (years)  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Merced County Association of Governments Janet Kasper (209) 385-7600   JKasper@co.merced.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$152 $0 $152
Non-bond Funding
State/Federal*
$100 $72 $172
 
Total**** $252 $72 $324

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$252 $72 $324 $324 $324 $0
 
Total* $252 $72 $324 $324 $324 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

09/01/2008 
10/26/2009 

05/28/2010 
09/22/2009 

05/15/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2008 

10/01/2008 
10/26/2009 

10/26/2009 
11/30/2009 

06/30/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 20
Increase System Reliability
Increase System Reliability (percent) 20
Reduced Operating/Maintenance Cost
Useful Life (years) 15

Bond Funding Cost
Adopted:
$152,000
Current Approved:
$152,000
Actual Expenditures:
$152,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31