MST Farebox System Modernization & Expansion

Description: Farebox Modernization & Expansion

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey
City Monterey
Zip Code 93940
 
Senate District
15
Assembly District 27
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability (percent)  4      
Increased Ridership      5  
Useful Life (years)  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Monterey-Salinas Transit Hunter Harvath (831) 393-8129   hharvath@mst.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $28 $28
PTMISEA-99313
$644 $0 $644
Non-bond Funding
Local**
$2,007 $-1,023 $984
 
Total**** $2,651 $-995 $1,657

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,651 $-995 $1,657 $672 $672 $984
 
Total* $2,651 $-995 $1,657 $672 $672 $984

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2008 

05/31/2009 
09/20/2010 

09/20/2010 
05/01/2010 

04/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

06/30/2009 
11/04/2011 

11/04/2011 
05/01/2011 

10/31/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability (percent) 4
Increased Ridership 5
Useful Life (years) 15

Bond Funding Cost
Adopted:
$643,942
Current Approved:
$643,942
Actual Expenditures:
$643,942

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31