Caltrans Logo

Town of Truckee Transit Vehicle Purchase

Description: Purchase Type 1b and Type 7 Transit Vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Nevada City
Zip Code 95959
 
Senate District
04
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Number of Buses Purchased for Replacment  2      
Useful Life (years)  7      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Nevada County Transportation Commission Daniel B. Landon (530) 265-3202   dlandon@nccn.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$129 $0 $129
Non-bond Funding
Local**
$0 $0 $0
 
Total**** $129 $3 $132

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$129 $3 $132 $174 $174 $-42
 
Total* $129 $3 $132 $174 $174 $-42

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2008 

 
09/14/2009 

09/14/2009 
10/23/2008 

04/30/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
 

07/01/2008 
09/14/2009 

09/14/2009 
07/30/2009 

08/30/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Number of Buses Purchased for Replacment 2
Useful Life (years) 7

Bond Funding Cost
Adopted:
$129,404
Current Approved:
$129,404
Actual Expenditures:
$129,404

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31