Diablo Valley College Transit Center

Description: Construct 10-bay transit center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Pleasant Hill
Zip Code 94520
 
Senate District
07
Assembly District 11
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)  10      
Increased Ridership        
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Central Contra Costa Transit Authority Celinda Dahlgren (925)676-1976 X205   cdahlgren@cccta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $38 $38
PTMISEA-99313
$1,089 $-584 $505
PTMISEA-99314
$53 $0 $53
Non-bond Funding
State/Federal*
$1,338 $-86 $1,251
Local**
$753 $97 $850
 
Total**** $3,232 $-535 $2,697

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$353 $-100 $253 $132 $132 $121
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,879 $-435 $2,444 $2,565 $2,565 $-121
 
Total* $3,232 $-535 $2,697 $2,697 $2,697 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
11/07/2011 

11/07/2011 
06/01/2009 

06/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
11/07/2011 

11/07/2011 
06/01/2009 

06/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

03/01/2009 
11/07/2011 

11/07/2011 
06/30/2010 

09/30/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

08/01/2009 
11/07/2011 

11/07/2011 
09/30/2010 

06/30/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent) 10
Increased Ridership
Useful Life (years) 20

Bond Funding Cost
Adopted:
$1,141,853
Current Approved:
$596,018
Actual Expenditures:
$596,018

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31