Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SFMTA Operator Restrooms |
Description: Project will result in approximately 4 restrooms to be used exclusively by Muni transit operators.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco |
Zip Code | 94103 |
Senate District |
03, 08 |
Assembly District | 12, 13 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
San Francisco Municipal Transportation Agency | Joel Goldberg | (415) 701-4499 | joel.goldberg@sfmta.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$186 | $0 | $186 | ||||
PTMISEA-99314 |
$2,965 | $-756 | $2,209 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $63 | $63 | ||||
Local** |
$0 | $4,280 | $4,280 | ||||
Total**** | $3,151 | $3,587 | $6,738 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,151 | $3,587 | $6,738 | $6,738 | $6,738 | $0 | |
Total* | $3,151 | $3,587 | $6,738 | $6,738 | $6,738 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/2008 06/01/2009 |
08/16/2010 |
09/01/2008 02/01/2011 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2009 03/01/2010 |
03/07/2014 11/28/2012 |
02/01/2012 08/30/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2010 02/01/2011 |
09/02/2014 10/14/2016 |
04/01/2014 03/31/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2011 06/01/2011 |
10/14/2016 10/14/2016 |
04/30/2017 07/31/2017 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,150,920 |
Current Approved: |
$2,394,904 |
Actual Expenditures: |
$2,394,904 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31