SFMTA Wayside Fare Collection Equipment

Description: Project will replace obsolete fare collection system at subway stations and surface stops to include the implementation of TransLink.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
03, 08
Assembly District 12, 13
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
Reduced Operating/Maintenance Cost      10  
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
San Francisco Municipal Transportation Agency Joel Goldberg (415) 701-4499   joel.goldberg@sfmta.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$1,000 $0 $1,000
Non-bond Funding
State/Federal*
$28,200 $-9,961 $18,239
Local**
$6,177 $-2,735 $3,442
 
Total**** $35,377 $-12,697 $22,680

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,648 $-1,648 $0 $0 $0 $0
Design(PS&E)
$5,000 $-5,000 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$28,729 $-6,049 $22,680 $22,680 $22,680 $0
 
Total* $35,377 $-12,697 $22,680 $22,680 $22,680 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

12/01/2009 
09/19/2014 

 
01/01/2008 

12/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2010 

12/01/2011 
09/19/2014 

08/16/2010 
11/01/2009 

08/31/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2012 

07/01/2012 
09/19/2014 

09/19/2014 
10/31/2012 

08/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)
Reduced Operating/Maintenance Cost 10
Useful Life (years) 20

Bond Funding Cost
Adopted:
$1,000,000
Current Approved:
$1,000,000
Actual Expenditures:
$1,000,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31