MacArthur Transit Village Plaza Improvements

Description: Renovation of the enrty plaza at the MacArthur BART Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
13, 16
Assembly District 03, 09
Congressional District 07, 08, 09, 10, 11, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA LEE (510) 464-6282   DLEE@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$29 $9 $37
PTMISEA-99313
$271 $62 $333
Non-bond Funding
State/Federal*
$2,069 $889 $2,958
Local**
$259 $5,169 $5,428
 
Total**** $2,628 $6,128 $8,756

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$100 $-100 $0 $0 $0 $0
Design(PS&E)
$259 $-259 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,269 $6,487 $8,756 $8,756 $8,756 $0
 
Total* $2,628 $6,128 $8,756 $8,756 $8,756 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

08/31/2009 
 

 
07/01/2007 

08/31/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2010 

12/31/2012 
 

 
02/01/2010 

12/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
02/01/2012 

05/31/2013 
 

03/04/2020 
02/01/2012 

04/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

12/31/2013 
03/04/2020 

03/04/2020 
04/30/2019 

12/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 1

Bond Funding Cost
Adopted:
$299,724
Current Approved:
$332,534
Actual Expenditures:
$332,534

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31