BART Ashby Elevator

Description: Project is to construct a new elevator at Ashby Station to accomodate the Ed Roberts campus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94604
 
Senate District
03, 09
Assembly District 13, 16
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
San Francisco Bay Area Rapid Transit District Kenneth A. Duron (510) 464-6083   boardofdirectors@bart.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$2,000 $-271 $1,729
Non-bond Funding
State/Federal*
$4,000 $-2,297 $1,703
Local**
$1,000 $-20 $980
 
Total**** $7,000 $-2,588 $4,412

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$500 $285 $785 $785 $785 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,500 $-2,873 $3,627 $3,627 $3,627 $0
 
Total* $7,000 $-2,588 $4,412 $4,412 $4,412 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2007 

04/01/2008 
 

01/02/2013 
11/01/2007 

09/23/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2008 

04/01/2010 
08/13/2010 

01/02/2013 
03/16/2009 

11/23/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2010 

06/01/2011 
03/06/2012 

01/02/2013 
12/02/2011 

11/30/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)

Bond Funding Cost
Adopted:
$2,000,000
Current Approved:
$1,729,046
Actual Expenditures:
$1,729,046

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31