Caltrans Logo

City of Vallejo Ferry Dredging

Description: Project will fund dredging work in order to ensure safe and continued operation of the Baylink Ferry service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Vallejo
Zip Code 94590
 
Senate District
02
Assembly District 11
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost        
Safety Improvement (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Vallejo Crystal Odum Ford 707-648-5241   codumford@ci.vallejo.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$200 $0 $200
Non-bond Funding
State/Federal*
$720 $-67 $653
 
Total**** $920 $-67 $853

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$920 $-67 $853 $853 $853 $0
 
Total* $920 $-67 $853 $853 $853 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/15/2008 

10/15/2008 
 

 
09/15/2008 

10/15/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost
Safety Improvement (percent)

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$200,000
Actual Expenditures:
$200,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31