Caltrans Logo

Ahern-12th Street Improvements

Description: "Sacramento - re-engineer timing of crossing activation, adding additional control features & changing control marking of the crossing for the LRT crossing."

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95814
 
Senate District
05, 06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Safety Improvement (percent)        
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Sacramento Area Council of Governments (SACOG) Gary Taylor (916) 340-6279   gtaylor@sacog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$70 $-16 $54
Non-bond Funding
State/Federal*
$0 $119 $119
 
Total**** $70 $104 $174

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $99 $99 $99 $99 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$70 $5 $75 $75 $75 $0
 
Total* $70 $104 $174 $174 $174 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

12/01/2009 
 

03/27/2012 
10/01/2008 

04/01/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2010 

03/01/2010 
03/27/2012 

03/27/2012 
05/01/2011 

03/01/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Safety Improvement (percent)
Useful Life (years) 20

Bond Funding Cost
Adopted:
$70,000
Current Approved:
$54,485
Actual Expenditures:
$54,485

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31