ADA Transit Plan Improvements

Description: Install detectable warning tile on either side of rail RR Xing where they intersect with pedestrians sidewalks

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95814
 
Senate District
05, 06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Percent of existing system Modernized        
Safety Improvement (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Sacramento Area Council of Governments (SACOG) Gary Taylor (916) 340-6279   gtaylor@sacog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$300 $-93 $207
Non-bond Funding
State/Federal*
$0 $422 $422
Local**
$0 $66 $66
 
Total**** $300 $395 $695

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $488 $488 $0 $0 $488
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$300 $-93 $207 $695 $695 $-488
 
Total* $300 $395 $695 $695 $695 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
60   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

12/01/2009 
 

10/04/2018 
10/01/2008 

05/15/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2010 

03/01/2010 
10/04/2018 

10/04/2018 
05/15/2018 

05/31/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Percent of existing system Modernized
Safety Improvement (percent)

Bond Funding Cost
Adopted:
$300,000
Current Approved:
$207,284
Actual Expenditures:
$207,284

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31