Replacement Parking @ Rocklin Multi-Modal Station

Description: Provide safe & convenient replacement parking for transit patrons

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01, 04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
Reduced Operating/Maintenance Cost        
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Placer County Transportation Planning Agency David Melko (530) 823-4030   dmelko@pctpa.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$179 $1 $180
Non-bond Funding
Local**
$20 $-20 $0
 
Total**** $199 $-12 $187

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $-5 $0 $0 $0 $0
Design(PS&E)
$15 $57 $72 $72 $72 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$179 $-64 $115 $115 $115 $0
 
Total* $199 $-12 $187 $187 $187 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/15/2008 

05/30/2008 
 

 
09/30/2010 

03/30/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/15/2008 

06/15/2008 
 

 
09/30/2010 

06/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/30/2008 

09/30/2008 
 

 
09/30/2008 

11/30/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
10/15/2008 

11/30/2008 
03/30/2012 

03/30/2012 
04/30/2011 

06/30/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)
Reduced Operating/Maintenance Cost
Useful Life (years) 20

Bond Funding Cost
Adopted:
$178,810
Current Approved:
$179,553
Actual Expenditures:
$179,553

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31