Green Metrolink Station Rehab Plan

Description: Rehab Riverside County Metrolink Stations with Green Technologies

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92501
 
Senate District
31, 37
Assembly District 64, 66, 71
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    10  
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Riverside County Transportation Commission Sheldon Peterson (951) 787-7928   speterson@rctc.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$2,478 $60 $2,538
Non-bond Funding
 
Total**** $2,478 $60 $2,538

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $344 $344 $-344
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,478 $60 $2,538 $2,194 $2,194 $344
 
Total* $2,478 $60 $2,538 $2,538 $2,538 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/10/2008 

 
 

 
04/10/2008 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2008 

06/30/2010 
 

03/23/2011 
07/01/2008 

03/31/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

07/30/2010 
03/23/2011 

03/23/2011 
03/31/2011 

05/31/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 10
Useful Life (years) 30

Bond Funding Cost
Adopted:
$2,477,714
Current Approved:
$2,537,980
Actual Expenditures:
$2,537,980

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31