Caltrans Logo

Purchase Replacement Bus

Description: Purchase 1 Replacement cutaway bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Banning
Zip Code 92220
 
Senate District
37
Assembly District 65, 80
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
Reduced Operating/Maintenance Cost  25    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Banning Bonnie J. Johnson (951) 922-3252   bjohnson@ci.banning.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$12 $0 $12
Non-bond Funding
State/Federal*
$65 $0 $65
 
Total**** $77 $0 $77

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$77 $0 $77 $12 $12 $65
 
Total* $77 $0 $77 $12 $12 $65

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2008 

12/01/2008 
07/03/2013 

07/03/2013 
03/26/2010 

05/06/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2009 

01/01/2009 
07/03/2013 

07/03/2013 
05/06/2010 

06/04/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3
Reduced Operating/Maintenance Cost 25 25

Bond Funding Cost
Adopted:
$11,820
Current Approved:
$11,820
Actual Expenditures:
$11,820

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31