Caltrans Logo

Procurment of Rolling Stock

Description: Purchase 3 Dial-a-Ride Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Corona
Zip Code 92882
 
Senate District
37
Assembly District 71
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      20  
Reduced Emissions      15  
Reduced Operating/Maintenance Cost  8    15  
Useful Life (years)  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Corona Robert Morin (951) 736-2446   robertm@ci.corona.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $40 $40
PTMISEA-99313
$184 $298 $482
PTMISEA-99314
$26 $15 $40
Non-bond Funding
State/Federal*
$0 $446 $446
 
Total**** $210 $798 $1,008

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$210 $798 $1,008 $562 $562 $447
 
Total* $210 $798 $1,008 $562 $562 $447

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

09/01/2008 
03/08/2012 

08/28/2012 
12/01/2011 

06/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

09/01/2009 
02/22/2013 

02/22/2013 
10/01/2012 

12/06/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Reduced Emissions 15
Reduced Operating/Maintenance Cost 8 15
Useful Life (years) 5

Bond Funding Cost
Adopted:
$210,000
Current Approved:
$522,552
Actual Expenditures:
$522,552

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31