MBTA (2) 30 Passenger Bus Procurement

Description: Purchase 2 - 30 Passenger CNG buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Joshua Tree
Zip Code 92252
 
Senate District
18
Assembly District 65
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      1  
Number of Buses Purchased for Replacment  2      
Reduced Operating/Maintenance Cost  3      
Useful Life (years)  7      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Morongo Basin Transit Authority Joe G. Meer (760) 366-2986   joe@mbtabus.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $4 $4
PTMISEA-99313
$246 $0 $246
PTMISEA-99314
$49 $0 $49
Non-bond Funding
 
Total**** $295 $4 $299

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$295 $4 $299 $299 $299 $0
 
Total* $295 $4 $299 $299 $299 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

11/01/2008 
07/17/2012 

07/17/2012 
11/01/2009 

03/17/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2008 

01/01/2009 
07/17/2012 

07/17/2012 
03/17/2011 

03/17/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1
Number of Buses Purchased for Replacment 2
Reduced Operating/Maintenance Cost 3
Useful Life (years) 7

Bond Funding Cost
Adopted:
$295,000
Current Approved:
$295,000
Actual Expenditures:
$295,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31