Caltrans Logo

Purchase Transit Cutaway Bus

Description: Purchase Transit Bus in the City of Escalon

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  25      
Number of Buses Purchased for Replacment  1      
Reduced Operating/Maintenance Cost        
Useful Life (years)  7      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
San Joaquin Council of Governments Tanisha Taylor (209) 468-3913   taylor@sjcog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$68 $-2 $67
Non-bond Funding
Local**
$0 $2 $2
 
Total**** $68 $-0 $68

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$68 $-0 $68 $67 $67 $2
 
Total* $68 $-0 $68 $67 $67 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2008 

12/01/2008 
09/14/2009 

09/14/2009 
11/03/2008 

12/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
12/02/2008 

12/31/2008 
03/29/2010 

03/29/2010 
03/01/2010 

04/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 25
Number of Buses Purchased for Replacment 1
Reduced Operating/Maintenance Cost
Useful Life (years) 7

Bond Funding Cost
Adopted:
$68,363
Current Approved:
$66,830
Actual Expenditures:
$66,830

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31