Transit Center |
Description: Construct transit center
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Lompoc |
Zip Code | 93438 |
Senate District |
19 |
Assembly District | 33 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | |
Increase System Reliability (percent) | 10 | |
Increase in Ridership (percent) | 10 | |
Increased Ridership | 10 | |
Reduced Emissions | 5 | |
Reduced Operating/Maintenance Cost | 5 | |
Useful Life (years) | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
City of Lompoc Transit/Colt | Richard L. Fernbaugh | (805) 875-8268 | rfernbaugh@ci.lompoc.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $19 | $19 | ||||
PTMISEA-99313 |
$1,972 | $-1,194 | $778 | ||||
PTMISEA-99314 |
$57 | $-35 | $22 | ||||
Non-bond Funding | |||||||
State/Federal* |
$100 | $-100 | $0 | ||||
Local** |
$0 | $249 | $249 | ||||
Total**** | $2,130 | $-1,062 | $1,068 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$100 | $-100 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $50 | $50 | $64 | $64 | $-14 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,030 | $-1,012 | $1,018 | $1,004 | $1,004 | $14 | |
Total* | $2,130 | $-1,062 | $1,068 | $1,068 | $1,068 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2008 05/31/2009 |
03/29/2017 |
06/01/2008 12/30/2015 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2009 05/31/2010 |
03/29/2017 03/29/2017 |
01/30/2016 06/30/2017 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2009 05/31/2010 |
03/29/2017 03/29/2017 |
06/01/2017 06/30/2017 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/15/2010 03/31/2011 |
05/04/2018 05/04/2018 |
10/01/2017 03/31/2018 |
90 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2011 06/30/2011 |
05/04/2018 05/04/2018 |
04/01/2018 04/30/2018 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | |
Increase System Reliability (percent) | 10 | |
Increase in Ridership (percent) | 10 | |
Increased Ridership | 10 | |
Reduced Emissions | 5 | |
Reduced Operating/Maintenance Cost | 5 | |
Useful Life (years) | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,029,787 |
Current Approved: |
$800,000 |
Actual Expenditures: |
$800,000 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31