Yolobus Rehab. & Repower 9 Transit Buses

Description: Rehab & Repower nine transit buses in a quarter of the time & funding of purchasing new replacements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yolo
City
Zip Code 95776
 
Senate District
05
Assembly District 02, 08
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Extend Vehicle Life (years)  8      
Increased Ridership      1  
Reduce Emissions (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Yolo County Transportation District Kwai Reitz 530-661-0816   kreitz@yctd.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $9 $9
PTMISEA-99314
$164 $0 $164
Non-bond Funding
State/Federal*
$1,186 $1,032 $2,217
Local**
$0 $258 $258
 
Total**** $1,350 $1,299 $2,649

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,350 $1,299 $2,649 $2,712 $2,712 $-64
 
Total* $1,350 $1,299 $2,649 $2,712 $2,712 $-64

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

08/01/2008 
 

 
07/01/2008 

08/01/2008 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2008 

01/30/2009 
 

04/30/2011 
09/01/2008 

01/30/2009 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2009 

09/30/2009 
 

 
02/01/2009 

09/30/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Extend Vehicle Life (years) 8
Increased Ridership 1
Reduce Emissions (percent)

Bond Funding Cost
Adopted:
$164,224
Current Approved:
$164,224
Actual Expenditures:
$164,224

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31