Purchase 2 CNG buses 1 gas 1 CNG Trolley

Description: Purchase 3CNG buses/trolley 1 gas bus ROTA riverbank

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95358
 
Senate District
12
Assembly District 25
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  50      
Number of Buses Purchased for Replacment  4      
Useful Life (years)  7      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Stanislaus Council of Governments Carlos Yamzon (209) 525-4600   cyamzon@stancog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$397 $-43 $354
Non-bond Funding
 
Total**** $397 $-43 $354

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$397 $-43 $354 $354 $354 $0
 
Total* $397 $-43 $354 $354 $354 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2008 

11/01/2008 
 

 
07/01/2008 

11/01/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2008 

11/01/2008 
11/05/2009 

11/05/2009 
07/01/2008 

11/01/2008 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 50
Number of Buses Purchased for Replacment 4
Useful Life (years) 7

Bond Funding Cost
Adopted:
$397,000
Current Approved:
$354,279
Actual Expenditures:
$354,279

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31