2 40 ft. CNG Heavy Duty Transit Buses

Description: Purchase 2 CNG buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12
Assembly District 25
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)  5      
Increased Ridership        
Number of Buses Purchased for Replacment  2      
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Stanislaus County Public Works-Transit Division Doralee Boles (209) 525-7504   bolesd@mail.co.stanislaus.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$101 $0 $101
Non-bond Funding
State/Federal*
$817 $-0 $817
Local**
$0 $1 $1
 
Total**** $918 $1 $919

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$918 $1 $919 $919 $919 $0
 
Total* $918 $1 $919 $919 $919 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

06/01/2009 
 

 
04/01/2008 

06/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2009 

12/31/2009 
 

 
12/01/2009 

12/31/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent) 5
Increased Ridership
Number of Buses Purchased for Replacment 2
Useful Life (years) 12

Bond Funding Cost
Adopted:
$101,341
Current Approved:
$101,341
Actual Expenditures:
$101,341

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31