Compressed Natural Gas Transit Bus (35ft.)

Description: Purchase CNG transit bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
12
Assembly District 26
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Number of New Buses Purchased for Expansion  1      
Reduce Emissions (percent)        
Reduced Emissions        
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Turlock Roger Fall (209) 668-5520   rfall@turlock.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $14 $14
PTMISEA-99313
$495 $-2 $493
Non-bond Funding
 
Total**** $495 $12 $507

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$495 $12 $507 $505 $505 $2
 
Total* $495 $12 $507 $505 $505 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

10/01/2008 
10/08/2009 

04/21/2010 
01/08/2009 

08/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2008 

02/01/2009 
03/14/2011 

09/29/2011 
01/01/2011 

09/30/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of New Buses Purchased for Expansion 1
Reduce Emissions (percent)
Reduced Emissions
Useful Life (years) 12

Bond Funding Cost
Adopted:
$495,495
Current Approved:
$493,221
Actual Expenditures:
$493,221

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31